Schedule Risk Evaluation and Control Countermeasures for Supporting Infrastructure Projects of Large-Scale Equipment based on ISM-BN

Authors

  • Dong Nie

DOI:

https://doi.org/10.6981/FEM.202606_7(6).0006

Keywords:

Large-scale Equipment Supporting Infrastructure Projects; Owner's Perspective; Schedule Risk Control; ISM-BN.

Abstract

To address the issues of vague schedule risk identification, insufficient quantitative research, and poorly targeted control measures in supporting infrastructure projects for large-scale equipment, this paper takes the perspective of the owner (the construction unit) as the starting point. Through expert interviews, a set of risk factors for such projects is identified and established. Using Interpretive Structural Modeling (ISM), the hierarchical relationships and propagation paths of schedule risks are revealed. A Bayesian Network (BN) model is then constructed for quantitative analysis to identify key risk nodes and causal chains, and to determine and classify schedule risk levels. Based on a comprehensive evaluation, targeted risk control measures are proposed, providing a reference for the owner's schedule management.

Downloads

Download data is not yet available.

References

[1] Gou, Q. Y., Deng, M. Q., Hu, K. K., et al. (2024). Construction of a risk evaluation index system for radar site engineering construction based on grey-rough set. Project Management Technology, 22(11), 102–107.

[2] Zhang, X. F., Wu, S. L., & Liu, Z. F. (2018). Study on the construction and evaluation of position engineering on the China-India border. Engineering and Technological Research, (4), 199–200.

[3] Du, M. Y. (2025). Optimization of penetrating schedule control for construction projects from the owner's perspective. Urban Development, (20), 100–102.

[4] Chen, X. N. (2025). Analysis of difficulties and innovative strategies in project management from the owner's perspective. Create Living, (9), 193–195.

[5] Zhang, J. (2025). Research on construction site management of primary and secondary school buildings from the owner's perspective. China Construction, (7), 20–22.

[6] Zhao, B., & Zhong, C. L. (2022). Research on influencing factors of schedule control of prefabricated buildings based on ISM. Journal of Jilin Jianzhu University, 39(6), 56–64.

[7] Chen, J., Zhao, P. W., Zhang, M. K., et al. (2022). Research on influencing factors of university infrastructure project schedule based on ISM model. Construction Economy, 43(S1), 337–341.

[8] Chen, N. (2015). ISM analysis of factors influencing project schedule. Technology Innovation and Application, (23), 274.

[9] Cai, Z. L., Zhang, K., Li, B., et al. (2022). Research on schedule risk management in the renovation of old residential high-rise buildings based on Bayesian network. Construction Economy, 43(11), 60–66.

[10] Chen, Y., Jin, R., & Zha, Y. C. (2022). Research on delay risk of large complex public projects based on Bayesian network. Journal of Zhengzhou University (Engineering Science), 43(2), 91–97.

[11] Lin, Z. Z. (2025). Research on schedule risk management of housing construction project based on Bayesian network. Fujian Construction, (6), 107–110.

Downloads

Published

2026-06-11

Issue

Section

Articles

How to Cite

Nie, D. (2026). Schedule Risk Evaluation and Control Countermeasures for Supporting Infrastructure Projects of Large-Scale Equipment based on ISM-BN. Frontiers in Economics and Management, 7(6), 41-48. https://doi.org/10.6981/FEM.202606_7(6).0006